WIX ANA Network Operations Report
03/19/2018 - 03/25/2018

WIX ANA Network Operations Center
at Indiana University

New Connections

None


Upgrades

None


New Services

None


Unscheduled Outages Summary

Ticket Number Customer Impact Network Impact Title Outage Type Source Of Impact Start Time (UTC) End Time (UTC)


None during this report period

Scheduled Maintenances Summary

Ticket Number Customer Impact Network Impact Title Maintenance Type Source Of Impact Start Time (UTC) End Time (UTC)

952 3-Elevated 3-Elevated Maintenance - WIX ANA (London) Circuit Vendor03/25/2018 1:50 PM 03/25/2018 1:52 PM

Scheduled Maintenances Detail

Ticket No.:952:130
Subject:Maintenance - WIX ANA (London)
Source Of Impact:Vendor
Affected:Trans-Atlantic ANA-100 WIX-London
Start Time:Sunday, March 25, 2018, 1:50 PM (1350) UTC
End Time:Sunday, March 25, 2018, 1:52 PM (1352) UTC
Description: The above listed asset will be unavailable while TATA Communications Engineers perform maintenance in order to repair a shunt fault on the transatlantic cable segment. A long duration outage is expected. As this is submarine section work, it is scheduled for 21 days and the work is subjected to weather conditions.


Downtime and Availability



WIX ANA Core NodesDown TimeReporting Period Availability52 Week Availability
sw.net.wix.internet2.edu0 hr 0 min100.00000%99.46494%

Aggregate WIX ANA Core Nodes0 hr 0 min100.00000%99.46494%

WIX ANA Backbone CircuitsDown TimeReporting Period Availability52 Week Availability
WIX-ASHB-LOND-100GE-015300 hr 2 min99.98016%98.95283%

Aggregate All WIX ANA Backbone Circuits0 hr 2 min99.98016%98.95283%




Upcoming Scheduled Maintenances