MANLAN Network Operations Report
2019-05-20 - 2019-05-26
MANLAN Network Operations Center
| Connector | Type | Date | Sponsor |
|---|
None
None
None
| Incident Number | Customer Impact | Network Impact | Title | Outage Type | Source of Impact | Current State | Start Time (UTC) | End Time (UTC) | Duration |
|---|---|---|---|---|---|---|---|---|---|
| Ticket Number | Customer Impact | Network Impact | Title | Maintenance Type | Source Of Impact | Current State | Start Time (UTC) | End Time (UTC) | Duration |
|---|---|---|---|---|---|---|---|---|---|
| CHG0036472 | 3 - Moderate | 3 - Normal | Maintenance Completed - MANLAN ANA NEWY32AOA-Paris | Customer | Internal | Closed | 2019-05-21 16:20:19 | 2019-05-21 16:28:26 | 0 days 0 hr 8 min |
| Ticket No.: | CHG0036472 |
| Subject: | Maintenance Completed - MANLAN ANA NEWY32AOA-Paris |
| Source Of Impact: | Internal |
| Affected: | MAN-NEWY32AOA-PARIS-100GE-01667
I2-DENV-NEWY32AOA-VLAN-57967 ANA NEWY32AOA-Paris IP Participant GEANT |
| Current State: | Closed |
| Start Time: | 2019-05-21 16:20:19 |
| End Time: | 2019-05-21 16:28:26 |
| Description | The listed asset is available after Customer Engineers performed software upgrade maintenance. Maintenance has been completed. No further outages are anticipated. |
| MANLAN Nodes | Down Time | Reporting Period Availability | 52 Week Availability |
| sw.net.manlan.internet2.edu | 00 hr 00 min | 00 hr 00 min | 100.00000% | 100.00000% | 100.00000% | 100.00000% |
| Aggregate MANLAN Core Nodes | 0 days 0 hr 0 min | 0 days 0 hr 0 min | 100.00000% | 100.00000% | 100.00000% | 100.00000% |
NOTE: Numbers in italics represent downtime with scheduled maintenance excluded.
| MANLAN Backbone Circuits | Down Time | Reporting Period Availability | 52 Week Availability |
| MAN-NEWY32AOA-PARIS-100GE-01667 | 0 hr 8 min | 00 hr 00 min | 99.91948% | 100.00000% | 99.61766% | 99.61766% |
| Aggregate All MANLAN Backbone Circuits | 0 days 0 hr 8 min |0 days 0 hr 0 min | 99.91948% | 100.00000% | 99.61766% | 99.61766% |
NOTE: Numbers in italics represent downtime with scheduled maintenance excluded.
| MANLAN Backbone Circuits | Down Time | Reporting Period Availability | 52 Week Availability |
| MAN-S01668 - GEANT connection to Paris | |||
| MAN-NEWY32AOA-PARIS-100GE-01667 | 0 hr 8 min | 99.91948% | 99.61766% |