Indiana GigaPOP Network Operations Report
2020-02-21 - 2020-03-05

Indiana GigaPOP Network Operations Center

Unscheduled Outages Summary

Incident Number Customer Impact Network Impact Title Outage Type Source of Impact Current State Start Time (UTC) End Time (UTC) Duration


Unscheduled Outages Detail


None during this report period


Upcoming Scheduled Maintenances

Ticket No.:CHG0041409
Subject:Maintenance - Indiana GigaPOP Various Backbones
Source Of Impact: Vendor
Affected:Backbone UL-111N
Backbone CHIC-ICTC
Backbone CHIC-EQCH
Backbone 111N-CRPN
Member Purdue University
Member Indiana University
Member IU Research Network
Peer University of Chicago
Peer FutureGrid
Peer University of Wisconsin at Madison
Peer OARnet
Peer University of Minnesota - Twin Cities
Peer University of Illinois at Urbana-Champaign
Peer Midwest-IX
Start Time:2020-03-13 05:00:00
End Time:2020-03-13 11:00:00
DescriptionThe listed will be unavailable while Vendor CenturyLink Engineers perform fiber maintenance to relocate backbone cable as mandated by IDOT due to a road construction project. The estimated GPS location of work is Crawford Ave. & West 156th Street in Markham, IL. LAT: 41.606331 LONG: -87.716840. An outage of up to four (4) hours is expected; however, the entire window is reserved.