I-Light Network Operations Report
2019-03-22 - 2019-04-04

I-Light Network Operations Center

Unscheduled Outages Summary

Incident Number Customer Impact Network Impact Title Outage Type Source of Impact Current State Start Time (UTC) End Time (UTC) Duration

INC0031829 2 - High2 - High Outage Resolved - I-Light Backbones CLMB-CROT and CLMB-NEWAUnannounced Maintenance Vendor Resolved 2019-04-03 04:02:24 2019-04-03 10:51:05 0 days 6 hr 48 min

Unscheduled Outages Detail


Ticket No.:INC0031829
Subject:Outage Resolved - I-Light Backbones CLMB-CROT and CLMB-NEWA
Source Of Impact: Vendor
Affected:ILN-CLMB-CROT-10GE-3836
ILN-CLMB-CROT-FIBR-03835
ILN-CLMB-NEWA-100GE-24295
Backbone CLMB-CROT
Backbone CLMB-NEWA
Member Hanover College
Indiana State University
Indiana University Southeast
Ivy Tech Evansville
Ivy Tech Indianapolis Central Office
Ivy Tech Sellersburg
Oakland City University
Rose Hulman Venture
St. Mary of the Woods College
University of Evansville
University of Southern Indiana
Vincennes University - Fort Branch
Vincennes University - Indiana Deaf School
Vincennes University - Jasper
Vincennes University - Plainfield
Vincennes University Aviation
Vincennes University Lebanon
WFWA - Fort Wayne
Current State:Resolved
Start Time:2019-04-03 04:02:24
End Time:2019-04-03 10:51:05
DescriptionBackbones CLMB-CROT and CLMB-NEWA are now available. I-Light and Zayo Engineers have been contacted and determined this outage was an extension of maintenance performed by Zayo tracked in CHG0035731. Zayo Engineers have confirmed they are hands off and no further outages are expected.