Ticket No.: | 11681:45 |
Subject: | Internet2 IP Network Core Node NEWY Maintenance |
Affected: | IP Backbone Circuit NEWY-WASH IP Backbone Circuit NEWY-CHIC Ciena Backbone Circuit BOST-NEWY Grooming Backbone Circuit PHIL-NEWY ESNet SDN Backbone Circuit CHIC-NEWY ESNet SDN Backbone Circuit NEWY-WASH Connector MAGPI |
Start Time: | Sunday, March 2, 2008, 5:00 AM (0500) UTC |
End Time: | Sunday, March 2, 2008, 11:00 AM (1100) UTC |
Description: | Level(3) will be mining out and removing all fibers
found disconnected in the Gateway and collocation fiber
trays. No outage is expected, but due to work being
performed in the same cable tray as our fiber, there is
a potential for downtime to occur. |
| |
Ticket No.: | 11688:45 |
Subject: | Internet2 IP Network Core Node NEWY Maintenance |
Affected: | IP Backbone Circuit NEWY-WASH IP Backbone Circuit NEWY-CHIC Ciena Backbone Circuit BOST-NEWY Grooming Backbone Circuit PHIL-NEWY ESNet SDN Backbone Circuit CHIC-NEWY ESNet SDN Backbone Circuit NEWY-WASH Connector MAGPI |
Start Time: | Monday, March 3, 2008, 5:00 AM (0500) UTC |
End Time: | Monday, March 3, 2008, 11:00 AM (1100) UTC |
Description: | Level(3) will be mining out and removing all fibers
found disconnected in the Gateway and collocation fiber
trays. No outage is expected, but due to work being
performed in the same cable tray as our fiber, there is
a potential for downtime to occur. Please note that
this is a second date for this work. |
| |